Chennai Metro Rail project aims at providing the people of
Chennai with a fast, reliable, convenient, efficient, modern and economical
mode of public transport, which is properly integrated with other forms of
public and private transport including buses, sub-urban trains etc.
The Chennai Metro Rail Limited (CMRL) will be the
stretch between Koyambedu and St. Thomas Mount Road. The estimated cost for
this project is Rs. 14,600 Crore. The current status of the project is about 50
per cent of track laying has been completed on the stretch. The elevated
stretch has eight stations, including Koyambedu and St. Thomas Mount Road. The
elevated has to accommodate a complex structure over Kathipara junction.
Simultaneously, pending civil work, including construction of stations and the
portion of the corridor over Kathipara junction, will go on and is expected to
be completed in six months. Till Now 75 per cent of the civil work is
completed, according to CMRL.
CMRL proposes to begin its trial run by July this year. According to CMRL, the
deadline for the elevated stretch is the first quarter of 2014. Engineers at
different Metro sites said a three to five month delay could be expected in the
project. A massive project will have to overcome different hurdles at various
points. Right from land acquisition to shortage of river sand for construction,
there are a host of issues, said an engineer working at one of the underground
stations in Anna Salai. However, CMRL maintained it was doing its best.
Simultaneously, pending civil work, including construction of stations and the
portion of the corridor over Kathipara junction, will go on and is expected to
be completed in six months. Till Now 75 per cent of the civil work is
completed, according to CMRL.
CMRL proposes to begin its trial run by July this year. According to CMRL, the
deadline for the elevated stretch is the first quarter of 2014. Engineers at
different Metro sites said a three to five month delay could be expected in the
project. A massive project will have to overcome different hurdles at various
points. Right from land acquisition to shortage of river sand for construction,
there are a host of issues, said an engineer working at one of the underground
stations in Anna Salai. However, CMRL maintained it was doing its best.
Simultaneously, pending civil work, including construction of stations and the
portion of the corridor over Kathipara junction, will go on and is expected to
be completed in six months. Till Now 75 per cent of the civil work is
completed, according to CMRL.
CMRL proposes to begin its trial run by July this year. According to CMRL, the
deadline for the elevated stretch is the first quarter of 2014. Engineers at
different Metro sites said a three to five month delay could be expected in the
project. A massive project will have to overcome different hurdles at various
points. Right from land acquisition to shortage of river sand for construction,
there are a host of issues, said an engineer working at one of the underground
stations in Anna Salai. However, CMRL maintained it was doing its best.
Simultaneously, pending civil work, including construction of stations and the
portion of the corridor over Kathipara junction, will go on and is expected to
be completed in six months. Till Now 75 per cent of the civil work is
completed, according to CMRL.
CMRL proposes to begin its trial run by July this year. According to CMRL, the
deadline for the elevated stretch is the first quarter of 2014. Engineers at
different Metro sites said a three to five month delay could be expected in the
project. A massive project will have to overcome different hurdles at various
points. Right from land acquisition to shortage of river sand for construction,
there are a host of issues, said an engineer working at one of the underground
stations in Anna Salai. However, CMRL maintained it was doing its best.The bridge-like structure will come up at a
height of about 25 metres above the road, and connect with the Metro corridor
on two sides of the clover leaf-shaped flyover. Work for the construction of
flyover has begun and will be completed in six months. Chennaities
are eagerly waiting to travel in their very own Chennai Metro Rails.
Constructers, builders, management staffs of Chennai Metro Rail Limited (CMRL)
are equally excited to bring up this project and finish it with grand success
of opening Chennai Metro Rails before the end of this year.
I hope these metro r more safer then other
ReplyDelete